Dear Eric Langton families,
We are writing to provide an update on construction at Eric Langton Elementary and to outline temporary changes to parking and traffic flow, in order to help you plan for safe and smooth drop-off and pick-up.
Drop-off and Pick-up Instructions
Ongoing on-site civil works, along with underground utility work on Edge Street, will significantly reduce parking at our school and create congestion over the next several weeks. Families should plan for delays and allow extra time for morning drop-off and afternoon pick-up.
Please review the following carefully (see map):
- Lot is closed: Most of the school’s parking lot will be closed for September while on-site civil works continue (marked in red).
- Family parking: Parking on 227th Street has been converted to a pick-up/drop-off zone with a 1-hour parking limit (marked in yellow).
- No family parking on site: There is no available parking for families anywhere on school grounds.
- Staff parking only: A small number of spaces remain for Eric Langton and James Best staff (permit required) in the reduced lot on Edge Street and by James Best (marked in orange). Unauthorized vehicles in these spaces may be fined or towed.
- Drop-off zone: A temporary drop-off/pick-up zone has been established through the school lot on Edge Street (marked in light blue). Flaggers will be on site directing traffic. Vehicles must keep moving – no idling, no waiting, no parking.
- Pedestrian access path: A temporary path is available from 227th Street to the school (marked in dark blue).
Construction Progress
Work on the school site has advanced well over the summer. The structural steel and roofing are complete, and the building is expected to be water-tight by the end of September. Mechanical and electrical installations are in progress on both levels, and interior finishing has begun (drywall, priming, flooring, and millwork). View drone footage of the construction progress here: https://www.youtube.com/watch?v=3X5w1HhcS3Y.
Off-site civil works on 121st Avenue and Edge Street are largely complete, and on-site civil works around the north and west parking areas are scheduled to finish by the end of September.
Finally, the private residential development next to the school has begun underground utility work on Edge Street, expected to continue through October.
Thank you for helping us keep traffic moving safely for all students and families during this busy transition. We appreciate your flexibility and support as we navigate these changes together.
For additional information about the Eric Langton Elementary Replacement Project, including regular updates for the community, visit the district website at https://www.sd42.ca/eric-langton-replacement-project/. Updates for our school community will continue to be shared directly through the Parent Portal and published on the school website.