With the start of the new school approaching, I wanted to provide an update on the new Eric Langton Elementary school, current site conditions (including the demolition zone), and important […]
Main Content
NEWS
April 17, 2026: Further Extension of 227th Street Access Closure
Dear Eric Langton families, We have been advised that, regretfully, the temporary closure of access from 227th Street will need to remain in place until Monday, May 4, 2026, due […]
April 2, 2026: Extension of 227th Street Access Closure
Dear Eric Langton families, I am writing to let you know that the temporary closure of access from 227th Street will need to be extended, as recent periods of heavy […]
March 10, 2026: Project Update – Temporary Closure of 227th Street Access
Dear Eric Langton families, As construction of the new school building enters its final stages, we want to share an important project update regarding site access. Beginning March 16, 2026, […]
February 12, 2026: Project Milestone and Site Access Changes
Dear Eric Langton families, Please see below an update regarding the progress of the school replacement project and upcoming changes to site access required for the final phase of construction. […]